- Home
- Community
- Road Program
- Current Program Activities
Current Program Activities
Repaving work Aug. 26, 2020 on Carmen Street, off Palmer Ave.
Updated Aug. 26, 2020
South Laurel Avenue, Phase IV
Substantially complete.
Project extended; Bauer Avenue restoration was included in conjunction with this project.
Winthrop Place, Between Brookside & Lynn
Substantially complete.
Estimated value: $200,000.
Coach Drive, Wagon Road, Surrey Drive & Carriage Drive
CDBG Grant received.
Project includes 3,000 linear foot of curbing replacement, ADA curb ramp installation and various drainage improvements.
Engineer estimate: $305,842
Status: under engineer review and design (Spring 2021)
Sidewalk improvements:
NJDOT grant submitted for sidewalk installations on Middle Road and Union Avenue intersection (Spring 2021)
Lynn Boulevard Lower side streets
Status: In planning stage, under engineer review (Spring 2021)
Streets include:
- Redwood Terrace
- Crescent Place
- Virginia Avenue
- Roland Place
- Coleridge Avenue
- Nevada Drive
- Brookside Avenue
- Winthrop Place (east side)
Additional streets may be added subject to available funds.
Fleetwood Drive Section
Status: project substantially completed ahead of schedule and under budget.
Streets include:
- Colgate Court
- Cornell Drive
- Dartmouth Drive
- Duke Lane
- Georgetown Lane
- Fleetwood Drive
Engineer estimate $2,026,700.
Liberty Place Streets
Status: substantially completed
Streets include:
- Liberty Place
- Oakview Drive
- Franklin Avenue
- Compton Avenue
- Hillside Avenue
- Rose Terrace
- Thorne Place
- Byrn Place
- Trumen Place
- Rapelye Place
- Hopkins Terrace
- Woody Terrace
- Sidney Terrace
- Ivadell Place
Engineer estimate $295,000
Beers Street
Status: In design phase, under engineer review (Spring 2021)
This project includes full width road restoration, curbing and driveway apron replacement in some areas, ADA curb ramp installations, various drainage improvements and crosswalk improvements near the school.
From Clark Street to Bethany Road
NJDOT Grant received: $270,000
Engineer estimate: $622,753.75
NJNG
Road Restoration Phase 1
Estimated value $2,169,500
Amherst, Annapolis, Bucknell, Lafayette and Stanford Drive. Restoration substantially completed
Road Restoration Phase 2 Hudson Streets - NJNG
Estimated value $2,300,500
Status: Road restoration currently underway at Hudson Avenue, Carmen Street, N. Clark St., Colman St, Curren St., Bank St, Hart St, River St. . Note, not all roads will experience full length restoration at this time.
Section E (See chart)
Substantially complete
Engineer estimate: $2,169,500
Section B (SEE CHART)
Substantially complete
Engineer estimate: $2,534,500
Bethany Road:
Substantially complete
Engineer estimate: $411,556.25
Lynn Boulevard
Substantially complete – expanded scope of work; asphalt restoration included from Middle road to Mountain Avenue in addition to the initial curbing and drainage work.
Estimated cost: $800,000.
Road Analysis
Status: 2019 survey completed.
2020 analysis and update pending (Fall 2020).
All existing municipal roads have been evaluated in 2019 and their conditions rated under nationally recognized standards. This evaluation work was done by T&M Engineers and a Roadbotics analysis program. T&M performs field analyses of roadways and Roadbotics provides a digital analysis of all roads in ten-foot intervals using newer technology with artificial intelligence. The field inspection results and digital data collected are combined with existing data to prioritize continued road work.
All sections to be revised.
Funding source: Capital budget, bond.
Estimated Bond Total: $5,565,556.25
Status: Approved
Funding source: Capital budget, bond.
Estimated Bond Total: $3,000,000|
Status: Approved