- Home
- Government
- Projects & Initiatives
- Road Program
- Current Program Activities
Current Program Activities
Road Work Update
August 31, 2022
In an August 31 update to the Township Committee, T & M Engineering reported the contractor is still on track to be substantially completed by week ending September 23, weather permitting. All punch list work will then take place and will be completed by the end of October.
To date, all concrete work has been completed on the roads.
Below is the schedule for milling and paving of the remaining roads:
Roland Place – Final paving week ending 9/9/22.
Pacific Terrace – Final paving week ending 9/9/22.
Ivy Place – Final paving week ending 9/9/22.
Cedar Avenue – Final paving week ending 9/9/22.
Hemingway Drive – Final paving week ending 9/9/22.
Monterey Drive (Remaining Portion) – Final paving week ending 9/9/22.
Larsen Lane – Final paving week ending 9/16/22.
Helfrich Lane – Final paving week ending 9/16/22.
Leocadia Court – Final paving week ending 9/16/22.
Mountain Avenue – Final paving week ending 9/16/22.
Striping of the roadways will then be completed by week ending 9/23/22.
As always, this is weather permitting and may change
Road Work Update
August 12, 2022
The Township Engineering firm has informed the Hazlet Township Committee that the 2022 road upgrade program should be substantially completed by September 23.
Final restoration should be done by October 28, depending on weather.
The following 13 roads have been completed to date
- Hemlock Drive
- Monmouth Drive
- Magnolia Avenue
- Lake Avenue
- Elm Avenue
- Birch Avenue
- Buttonwood Place
- Dale Court
- Spruce Street
- Fir Place
- Tara Lin Drive
- Rochelle Drive
- Stone Road
Below is the approximate completion for the remaining roads based on the schedule from the contractor and work completed to date:
- Appleton Drive – Concrete work is complete. Final paving week ending 8/19/2022.
- Cove Road – Concrete work is complete. Final paving week ending 8/19/22.
- Hilltop Place – Concrete work is complete. Final paving week ending 8/19/2022.
- Monterey Drive – Concrete work complete. Final paving week ending 8/19/2022.
- Larsen Lane – Concrete work is complete. Final paving week ending 9/9/22.
- Helfrich Lane – Concrete work is complete. Final paving week ending 9/9/22.
- Leocadia Court – Concrete work is complete. Final paving week ending 9/9/22.
- Mountain Avenue – Concrete work week ending 8/19/22. Final paving week ending 9/9/22.
- Hemingway Drive – Concrete work week ending 8/19/22. Final paving week ending 9/16/22.
- Ivy Place – Concrete work week ending 8/26/22. Final paving week ending 9/16/22.
- Cedar Avenue – Concrete work week ending 8/26/22. Final paving week ending 9/16/22.
- Roland Place – Concrete work week ending 9/2/22. Final paving week ending 9/16/22.
- Pacific Terrace – Concrete work week ending 9/2/22. Final paving week ending 9/23/22.
Road Work Ahead
May 20, 2022
Road work is underway in three Hazlet neighborhoods, as the Hazlet Township Committee's ambitious Road Restoration Program rolls on.
On Monday, Lucas Brothers Contractors will start work on Hemlock and surrounding streets, off Union Avenue. Over by Cove Road School, JF Kiely Contractors is currently installing a new NJNG main on Monterey. S. Brothers General Contractors is busy behind Airport Plaza, in the neighborhoods of Wagon Road; and Coach, Surrey and Carriage Drives, installing storm water drainage system improvements.
All of these areas will get new curbing and certain driveway aprons replaced as needed, as well as ADA compliant sidewalk ramps at intersections. The entire roadway surface will be milled and repaved and look brand new.
"Residents can expect to see a lot of work being done, and they will be able to see their tax dollars at work," said Mayor Michael Sachs.
Hazlet launched the Roadway Restoration Program in 2018 with a list of 110 municipal roads on the to-do list.
Repairs began in 2019 and are being completed in phases, in coordination with NJNG utility work when possible. The work is partially funded by NJDOT Municipal Aid Grant Program and financing from a Monmouth County Community Development Block Grant. T& M Engineering is overseeing the work.
Information about current program activities can be found on the township website. Visit the Road Program section.
2022 Program
Updated April 20, 2022
Appleton Drive Birch Avenue Buttonwood Place Cedar Avenue Cove Road Dale Court Elm Avenue Fir Place Helfrich Lane Hemingway Drive Hemlock Street Hilltop Place Ivy Place | Lake Avenue Larson Lane Leocadia Drive Magnolia Avenue Monmouth Street Monterey Drive Mountain Avenue Pacific Terrace Rochelle Drive Roland Place Spruce Street Stone Road Tara Lin Drive |
South Laurel Avenue, Phase IV
Substantially complete.
Project extended; Bauer Avenue restoration was included in conjunction with this project.
Winthrop Place, Between Brookside & Lynn
Substantially complete.
Estimated value: $200,000.
Coach Drive, Wagon Road, Surrey Drive & Carriage Drive
CDBG Grant received.
Project includes 3,000 linear foot of curbing replacement, ADA curb ramp installation and various drainage improvements.
Engineer estimate: $305,842
Status: under construction (Spring 2022)
Sidewalk improvements:
NJDOT grant for sidewalk installations on Middle Road and Union Avenue intersection (Completed.)
Lynn Boulevard Lower side streets
Status: Substantial completion
Streets include:
- Redwood Terrace
- Crescent Place
- Virginia Avenue
- Roland Place
- Coleridge Avenue
- Nevada Drive
- Brookside Avenue
- Winthrop Place (east side)
Additional streets may be added subject to available funds.
Fleetwood Drive Section
Status: project substantially completed ahead of schedule and under budget.
Streets include:
- Colgate Court
- Cornell Drive
- Dartmouth Drive
- Duke Lane
- Georgetown Lane
- Fleetwood Drive
Engineer estimate $2,026,700.
Liberty Place Streets
Status: substantially completed
Streets include:
- Liberty Place
- Oakview Drive
- Franklin Avenue
- Compton Avenue
- Hillside Avenue
- Rose Terrace
- Thorne Place
- Byrn Place
- Trumen Place
- Rapelye Place
- Hopkins Terrace
- Woody Terrace
- Sidney Terrace
- Ivadell Place
Engineer estimate $295,000
Beers Street
Status: Completed (Spring 2022)
This project includes full width road restoration, curbing and driveway apron replacement in some areas, ADA curb ramp installations, various drainage improvements and crosswalk improvements near the school.
From Clark Street to Bethany Road
NJDOT Grant received: $270,000
Engineer estimate: $622,753.75
NJNG
Road Restoration Phase 1
Estimated value $2,169,500
Amherst, Annapolis, Bucknell, Lafayette and Stanford Drive. Restoration substantially completed
Road Restoration Phase 2 Hudson Streets - NJNG
Estimated value $2,300,500
Status: Road restoration currently underway at Hudson Avenue, Carmen Street, N. Clark St., Colman St, Curren St., Bank St, Hart St. and River St. . Note, not all roads will experience full length restoration at this time.
Section E See chart
Substantially complete
Engineer estimate: $2,169,500
Section B SEE CHART
Substantially complete
Engineer estimate: $2,534,500
Bethany Road:
Substantially complete
Engineer estimate: $411,556.25
Lynn Boulevard
Substantially complete – expanded scope of work; asphalt restoration included from Middle road to Mountain Avenue in addition to the initial curbing and drainage work.
Estimated cost: $800,000.
Road Analysis
Status: 2021 survey completed.
All existing municipal roads have been evaluated in 2021 and their conditions rated under nationally recognized standards. This evaluation work was done by T&M Engineers.
Funding source: Capital budget, bond.
Estimated Bond Total: $5,565,556.25
Status: Approved
Funding source: Capital budget, bond.
Estimated Bond Total: $3,000,000|
Status: Approved